Daily Field Report
Date :09/02/2021
Project No :2021C073
Client Company :DR Horton West
Arrival Time :09/02/2021 07:30
Onsite Hours :02:00
Name of the Project :Tributary C2A
Project Location :Riverside Parkway, City of Douglasville, GA
Weather :Partly cloudy
Departure Time :09/02/2021 09:30
ASEC Technician Name :Christopher Burrow II
Observations/Finding
The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities.
The following are observations that were made at this time:
- Excavations made from the mining of structural fill was filled with unsuitable material. The excavation measured approximately 46’x87’x30’.
- The contractor started installing sewer laterals at lots 430 through 439.
- Some top soils was removed in the mining but the decision was made to not pursue this further.
Top soil encountered while trenching for sewer laterals
Top soil encountered while trenching for sewer laterals
Technician Signature / DateChristopher Burrow II, September 2, 2021
Reviewer Name / DateRamchandra Mogulla, March 29, 2023