Skip to content

Daily Field Report

Date :08/20/2021
Project No :2021C073
Client Company :DR Horton West
Arrival Time :08/20/2021 18:00
Onsite Hours :01:00
Name of the Project :Tributary C2A
Project Location :Riverside Parkway, City of Douglasville, GA
Weather :Partly cloudy
Departure Time :08/20/2021 19:00
ASEC Technician Name :Christopher Burrow II

Observations/Finding

As requested, a ASEC Inspector was present at the above referenced site for the purpose of observing the placement of structural fill at the area of lots 432, 433, and 423 approximate size 110 feet by 140 feet. Based on review of guidelines for fill placement, the required compaction for structural fill at the above mentioned area is 95 % of standard proctor. Based on visual observation and field measuring, the fill was placed in 8 to 12 inch thick lifts and compacted using CAT 815F sheepsfoot compactor(weight; 45,757 lbs.). Based on density testing, the fill placed today at elevations between approximately -6 feet and -0 feet below finished grade was compacted according to fill placement guidelines. See attached density test results for more details.

The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities. The following are observations that were made at this time: unsuitable soils continue to be piled on site to be used later in fill slopes and green areas. Lots 396 through 398 were excavated. Beginning structural fill placement on lots 399 and 400.

ASEC recommends sealing of the surface of placed fill from inclement weather and maintain the positive drainage.

The contractor was notified about results. 

Technician Signature / DateChristopher Burrow II, August 20, 2021
Reviewer Name / DateRamchandra Mogulla, March 29, 2023