Daily Field Report

Date :08/07/2021
Project No :2021C073
Client Company :DR Horton West
Arrival Time :08/07/2021 08:00
Onsite Hours :02:00
Name of the Project :Tributary C2A
Project Location :Riverside Parkway, City of Douglasville, GA
Weather :Partly cloudy
Departure Time :08/07/2021 10:00
ASEC Technician Name :Christopher Burrow II

Observations/Finding

The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities. The following are observations that were made at this time:

The contractor continued moving the soil mixed in with large amounts of organic material unacceptable for structural fill to the excavation as mentioned in the previous report.

Technician Signature / DateChristopher Burrow II, August 7, 2021
Reviewer Name / DateRamchandra Mogulla, March 29, 2023